Anna’s House in Byron Center
Description:
Project Summary:
At the start of 2024, Anna’s House restaurant in Byron Center began as a hollow shell with dirt floors. Swanson Electrical Services Inc. played a key role in transforming the space from unfinished to fully operational. Underground electrical work was completed in January, followed by wall rough-ins during the first weeks of February. In May, lighting fixtures and above-ceiling electrical were installed, finalizing the building’s electrical systems. This commercial project encompassed comprehensive electrical work from the initial phases to completion, preparing the space to welcome customers.
Location:
Byron Center, MI